United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· MISO

Solar project J1162, Jefferson County

Solar project J1162, Jefferson County is a 80.0 MW solar request withdrawn in the MISO interconnection queue, in Jefferson County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1162
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Jacinto - China 230 kV Line Tap
Location
Jefferson County, Texas
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
June 2020
Withdrawn
August 2019

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem