πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· MISO

Solar project J911, Montgomery County

Solar project J911, Montgomery County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Montgomery County, Texas, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J911
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Porter 230kV Substation
Location
Montgomery County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2020
Withdrawn
January 2019

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem