United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESGas interconnection queue in ERCOT (Texas)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Prairie Ridge (Gas - CC) Gas · Tenaska Power Generation, LLC |
1,660 MW | In study |
| Aegle Power Gas · Aegle Power LLC |
1,536 MW | In study |
| Caldwell County Energy Center Gas · Caldwell County Energy Center, LLC |
1,500 MW | In study |
| Mule Deer Run Gas Gas · BOULEVARD ASSOCIATES, LLC |
1,381 MW | In study |
| BasRanch (TEF - Due Diligence) Gas · CPV Basin Ranch, LLC |
1,350 MW | Agreement signed |
| Sandow Lakes Energy Station Gas · SL Energy Power Plant I, LLC |
1,292 MW | In study |
| Jewett Energy Center 1 Gas Gas · Jewett Energy Center LLC |
1,274 MW | In study |
| Tolar Energy Center Gas · NRG Tolar Power LLC |
1,252 MW | In study |
| Limitless Energy Hub I Gas · Limitless Energy Hub I LLC |
1,238 MW | In study |
| Limitless Energy Hub II Gas · Limitless Energy Hub II LLC |
1,238 MW | In study |
| Wolf Bone North Energy Center Gas · NRG Wolf Bone Energy Center LLC |
1,204 MW | In study |
| Eagle Pines Gas Gas · FGE Power |
1,174 MW | In study |
| Bastrop Peaking Generators (TEF-Due Diligence) Gas · MPH Bastrop Peakers, LLC |
1,104 MW | Agreement signed |
| EmberGreen Gas · EmberGreen Energy Center |
1,036 MW | In study |
| Black Mountain Hale Gas Gas · Fort Worth Power Core LLC |
991 MW | In study |
| Kilby1 Part 4 Large Block Simple Cycle Gas · Energy Forge One LLC |
950 MW | In study |
| Riviera Gas Gas · BKV-BPP Power |
942 MW | In study |
| EmberYork Gas · EmberYork Energy Center |
900 MW | Agreement signed |
| West Royal Natural Gas (TEF-Due Diligence) Gas · Invenergy Energy Transition Development LLC |
888 MW | In study |
| Sim Gideon Combined Cycle Gas · LCRA |
880 MW | In study |
| Lost Pines Power Park Gas · LCRA |
880 MW | In study |
| Schneider Combined Cycle Gas · LCRA |
880 MW | In study |
| MilamStation Power Secured Gas Generation Gas · Power Secured Holdings LLC |
846 MW | In study |
| Central Power Station Gas · Hydra-Gen Energy Unlimited |
750 MW | In study |
| FGE Texas 2 Gas Gas · FGE Power |
743 MW | Paused / redesign |
| Cedar Bayou 5 (TEF - Due Diligence) Gas · NRG Cedar Bayou 5 LLC |
697 MW | Agreement signed |
| Texpo Gas · Oklaunion Power Station, LLC |
680 MW | In study |
| Jack County III ‚Äì 345 kV Gas · Jack County Power Development, LLC |
660 MW | In study |
| Coleto Creek - Fuel Change Only Gas · COLETO CREEK POWER LLC |
655 MW | In study |
| Longleaf Power Station Gas · WattBridge Texas Holding, LLC |
600 MW | In study |
| RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) Gas · Rayburn Energy Station LLC |
570 MW | In study |
| Elmax Power Station Gas · Elmax Generating, LLC |
519 MW | Agreement signed |
| Fort Worth Power Core Bastrop Gas Plant Gas · Fort Worth Power Core LLC |
506 MW | In study |
| Black Mountain Somervell Gas Combined Gas · Fort Worth Power Core LLC |
495 MW | In study |
| Halyard Wharton Gas · Halyard Energy |
484 MW | Paused / redesign |
| North Royal Thermal (TEF- Due Diligence) Gas · Invenergy Energy Transition Development LLC |
479 MW | In study |
| Gregory Power Development SLF Gas · Gregory Power Partners LLC |
470 MW | In study |
| NRG THW GT 345 (Tef) Gas · NRG THW GT LLC |
456 MW | Agreement signed |
| TRIFECTA Gas Gas · NET Power |
453 MW | In study |
| Calpine Guadalupe Peakers Gas · Guadalupe Peaking Energy Center, LLC |
450 MW | In study |
| Big Watt Power Austin-1 Gas · Big Watt Power Austin-1 LLC |
449 MW | In study |
| NRG Greens Bayou 6 (TEF-Due Diligence) Gas · NRG Greens Bayou 6 LLC |
445 MW | Agreement signed |
| Vast Sands Power II (TEF-Due Diligence) Gas · Permian Power I LLC |
440 MW | Agreement signed |
| Vast Sands Power I (TEF -Due Diligence) Gas · Permian Power I LLC |
440 MW | Agreement signed |
| Exergy Energy West Texas Natural Gas Reciprocating Power I Gas · August Partners LLC |
400 MW | In study |
| Boling Generation (TEF-Due Diligience) Gas · Boling Generation |
400 MW | In study |
| Kilby1 Part 1 Small Block Simple Cycle Gas · Energy Forge One LLC |
371 MW | In study |
| Cielo Vista Power Gas Plant Gas · Cielo Vista Power, LLC |
335 MW | In study |
| River Boat Power Gas Plant Gas · Champion Creek Power, LLC |
334 MW | In study |
| Sky Global West Houston Gas · Sky Global Power Two, LLC |
325 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)116 · 70.9 GW
- Southeast (non-ISO utilities)214 · 65.0 GW
- ERCOT (Texas)104 · 45.7 GW
- SPP (Southwest Power Pool)78 · 35.0 GW
- West (non-ISO utilities)122 · 29.2 GW
- PJM (Mid-Atlantic, Midwest)44 · 14.0 GW
- CAISO (California)8 · 3,493 MW
- ISO-NE (New England)2 · 74.6 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)