Withdrawn queue requests in CAISO (California) (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16819.1 GW
Active in queue333 MW3 requests
Agreement signed333 MW3 requests
Withdrawn16819.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

168 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Eagle Mountain Pump Storage #2
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2016
Wildcat Quartszite
Solar
1,000 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2010target 2015
Palo Verde Mesa (Fka Brightsource Midpoint Solar)
Solar
750 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2015
Sutter Energy Center 2
Gas
600 MWWithdrawn / abandoned Sutter, CACAISO Feb 2010target 2018
Imperial Valley Generation Project
Gas
600 MWWithdrawn / abandoned Imperial, CACAISO Feb 2010target 2014
Valley Oak Solar
Solar
600 MWWithdrawn / abandoned Kings, CACAISO Jul 2010target 2015
El Dorado Valley Generation
Gas
600 MWWithdrawn / abandoned Clark, NVCAISO Feb 2010target 2014
Gila Solar
Solar
500 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2015
Re Austin
Solar
500 MWWithdrawn / abandoned Imperial, CACAISO Jul 2010target 2014
Cpa Maricopa Solar
Solar
500 MWWithdrawn / abandoned Kern, CACAISO Feb 2010target 2013
RRG Solar
Solar
480 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
FRV Eafb Solar
Solar
450 MWWithdrawn / abandoned Kern, CACAISO Feb 2010target 2013
Barstow Solar II
Solar
420 MWWithdrawn / abandoned San Bernardino, CACAISO Feb 2010target 2013
Panoche Valley Solar Farm Expansion
Solar
400 MWWithdrawn / abandoned San Benito, NVCAISO Feb 2010target 2013
TGP NNP
Geothermal
364 MWWithdrawn / abandoned Churchill, NVCAISO Jul 2010target 2016
Wre - Vestal (49/480MW)
Solar
320 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2013
Fort Mojave Solar
Solar
310 MWWithdrawn / abandoned Mojave, AZCAISO Feb 2010target 2019
Nevada 300
Solar
300 MWWithdrawn / abandoned Clark, NVCAISO Jul 2010target 2014
Arco Solar Station
Solar
300 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
Wre - Schindler
Other
289 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2017
Wre - Panoche
Other
289 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2017
Wre - Mendota
Solar
289 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2017
Brightsource Av Project
Solar
260 MWWithdrawn / abandoned Los Angeles, CACAISO Jul 2010target 2015
Silver Leaf Solar
Solar
250 MWWithdrawn / abandoned Imperial, CACAISO Jul 2010target 2013
Kingsolar II
Solar
250 MWWithdrawn / abandoned Kings, CACAISO Feb 2010target 2013
Copper Mountain Solar III (Black Hills)
Solar
242 MWWithdrawn / abandoned Clark, NVCAISO Jul 2010target 2013
Palmas (Fka Hyder Solar)
Solar
238 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2010target 2013
Placer Solar PV I
Solar
220 MWWithdrawn / abandoned Placer, CACAISO Jul 2010target 2014
Madera Solar PV I (Fka Wheeler Ridge Solar PV1)
Solar
220 MWWithdrawn / abandoned Madera, CACAISO Feb 2010target 2013
Blue SKY Wind Energy Center
Onshore wind
200 MWWithdrawn / abandoned Los Angeles, CACAISO Jul 2010target 2012
Airport Solar PV 1
Solar
200 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2013
Mount Signal Solar Farm II
Solar
200 MWWithdrawn / abandoned Imperial, CACAISO Jul 2010target 2014
Mount Signal Solar Farm
Solar
200 MWWithdrawn / abandoned Imperial, CACAISO Feb 2010target 2014
Westlands Solar PV I
Solar
200 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2014
Laguna Solar Farm
Solar
200 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2014
Blythe Solar PV I
Solar
170 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2012
Loma Verde Solar Energy Park
Solar
170 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2014
Wre - Stroud
Other
169 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2017
Alta 14
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
Antelope Valley Renewable Energy Farm - Solar
Solar
150 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2010target 2013
Angiola Valley Solar Ranch
Solar
150 MWWithdrawn / abandoned Kings, CACAISO Jul 2010target 2016
Antelope Valley Renewable Energy Farm - Wind
Onshore wind
150 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2010target 2014
Pacheco Pass Wind Energy Center
Onshore wind
150 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2014
Mojavalon I
Solar
146 MWWithdrawn / abandoned Kern, CACAISO Feb 2010target 2013
Timber Hills Wind (Fka Hillcrest Wind Power 1)
Onshore wind
138 MWWithdrawn / abandoned Shasta, CACAISO Feb 2010target 2013
Mayacmas Wind Power
Onshore wind
126 MWWithdrawn / abandoned Mendocino, CACAISO Feb 2010target 2013
Ord Mountain
Solar + storage
120 MWWithdrawn / abandoned San Bernardino, CACAISO Feb 2010target 2022
FRV Diamond Valley Solar
Solar
110 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2013
San Joaquin 1 & 2
Solar
107 MWWithdrawn / abandoned Fresno, CACAISO Feb 2010target 2012
Paradise Peak Wind Power Project
Onshore wind
102 MWWithdrawn / abandoned Shasta, CACAISO Feb 2010target 2012
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)