United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Eagle Mountain Pump Storage #2 Hydro |
1,400 MW | Withdrawn / abandoned |
| Wildcat Quartszite Solar |
1,000 MW | Withdrawn / abandoned |
| Palo Verde Mesa (Fka Brightsource Midpoint Solar) Solar |
750 MW | Withdrawn / abandoned |
| Sutter Energy Center 2 Gas |
600 MW | Withdrawn / abandoned |
| Imperial Valley Generation Project Gas |
600 MW | Withdrawn / abandoned |
| Valley Oak Solar Solar |
600 MW | Withdrawn / abandoned |
| El Dorado Valley Generation Gas |
600 MW | Withdrawn / abandoned |
| Gila Solar Solar |
500 MW | Withdrawn / abandoned |
| Re Austin Solar |
500 MW | Withdrawn / abandoned |
| Cpa Maricopa Solar Solar |
500 MW | Withdrawn / abandoned |
| RRG Solar Solar |
480 MW | Withdrawn / abandoned |
| FRV Eafb Solar Solar |
450 MW | Withdrawn / abandoned |
| Barstow Solar II Solar |
420 MW | Withdrawn / abandoned |
| Panoche Valley Solar Farm Expansion Solar |
400 MW | Withdrawn / abandoned |
| TGP NNP Geothermal |
364 MW | Withdrawn / abandoned |
| Wre - Vestal (49/480MW) Solar |
320 MW | Withdrawn / abandoned |
| Fort Mojave Solar Solar |
310 MW | Withdrawn / abandoned |
| Nevada 300 Solar |
300 MW | Withdrawn / abandoned |
| Arco Solar Station Solar |
300 MW | Withdrawn / abandoned |
| Wre - Schindler Other |
289 MW | Withdrawn / abandoned |
| Wre - Panoche Other |
289 MW | Withdrawn / abandoned |
| Wre - Mendota Solar |
289 MW | Withdrawn / abandoned |
| Brightsource Av Project Solar |
260 MW | Withdrawn / abandoned |
| Silver Leaf Solar Solar |
250 MW | Withdrawn / abandoned |
| Kingsolar II Solar |
250 MW | Withdrawn / abandoned |
| Copper Mountain Solar III (Black Hills) Solar |
242 MW | Withdrawn / abandoned |
| Palmas (Fka Hyder Solar) Solar |
238 MW | Withdrawn / abandoned |
| Placer Solar PV I Solar |
220 MW | Withdrawn / abandoned |
| Madera Solar PV I (Fka Wheeler Ridge Solar PV1) Solar |
220 MW | Withdrawn / abandoned |
| Blue SKY Wind Energy Center Onshore wind |
200 MW | Withdrawn / abandoned |
| Airport Solar PV 1 Solar |
200 MW | Withdrawn / abandoned |
| Mount Signal Solar Farm II Solar |
200 MW | Withdrawn / abandoned |
| Mount Signal Solar Farm Solar |
200 MW | Withdrawn / abandoned |
| Westlands Solar PV I Solar |
200 MW | Withdrawn / abandoned |
| Laguna Solar Farm Solar |
200 MW | Withdrawn / abandoned |
| Blythe Solar PV I Solar |
170 MW | Withdrawn / abandoned |
| Loma Verde Solar Energy Park Solar |
170 MW | Withdrawn / abandoned |
| Wre - Stroud Other |
169 MW | Withdrawn / abandoned |
| Alta 14 Solar |
150 MW | Withdrawn / abandoned |
| Antelope Valley Renewable Energy Farm - Solar Solar |
150 MW | Withdrawn / abandoned |
| Angiola Valley Solar Ranch Solar |
150 MW | Withdrawn / abandoned |
| Antelope Valley Renewable Energy Farm - Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Pacheco Pass Wind Energy Center Onshore wind |
150 MW | Withdrawn / abandoned |
| Mojavalon I Solar |
146 MW | Withdrawn / abandoned |
| Timber Hills Wind (Fka Hillcrest Wind Power 1) Onshore wind |
138 MW | Withdrawn / abandoned |
| Mayacmas Wind Power Onshore wind |
126 MW | Withdrawn / abandoned |
| Ord Mountain Solar + storage |
120 MW | Withdrawn / abandoned |
| FRV Diamond Valley Solar Solar |
110 MW | Withdrawn / abandoned |
| San Joaquin 1 & 2 Solar |
107 MW | Withdrawn / abandoned |
| Paradise Peak Wind Power Project Onshore wind |
102 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 Β· 22.6 GW
- PJM (Mid-Atlantic, Midwest)361 Β· 21.6 GW
- CAISO (California)168 Β· 19.1 GW
- Southeast (non-ISO utilities)18 Β· 11.1 GW
- MISO (Midcontinent)72 Β· 10.9 GW
- SPP (Southwest Power Pool)50 Β· 9,058 MW
- ERCOT (Texas)28 Β· 3,689 MW
- ISO-NE (New England)12 Β· 1,337 MW
- NYISO (New York)5 Β· 1,285 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)