🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Wre - Vestal (49/480MW)

Wre - Vestal (49/480MW) is a 320 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2010 (completed)
  2. Withdrawn / abandonedSep 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
643S
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vestal Sub 230 kV Bus
Location
Fresno County, California
Technology
Solar: 320 MW
Total requested
320 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 July 2010
Proposed online date
June 2013
Withdrawn
September 2011

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem