🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Madera Solar PV I (Fka Wheeler Ridge Solar PV1)

Madera Solar PV I (Fka Wheeler Ridge Solar PV1) is a 220 MW solar request withdrawn in the CAISO interconnection queue, in Madera County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandonedFeb 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
579
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Borden Sub 230kV bus
Location
Madera County, California
Technology
Solar: 220 MW
Total requested
220 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2010
Proposed online date
December 2013
Withdrawn
February 2011

Location

Marker shows the centre of Madera County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Madera County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem