United States › Grid › Interconnection queues › California
OTHER · CAISOChowchilla Biomass
Chowchilla Biomass is a 10.5 MW other request built and operating in the CAISO interconnection queue, in Madera County, California, connecting to PGAE.
Request details
- Queue ID
- 75
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Le Grand-Chowcilla 115 kV
- Location
- Madera County, California
- Technology
- Other: 10.5 MW
- Total requested
- 10.5 MW
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 15 July 2005
- Proposed online date
- December 2005
- Came online
- May 2009
Location
Marker shows the centre of Madera County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Madera County
- Lotus Solar 2Solar + storage · 406 MW · in study
- GaladrielBattery storage · 318 MW · in study
- Puma StorageBattery storage · 204 MW · in study
- Flores StorageBattery storage · 152 MW · in study
- Valetudo Energy StorageBattery storage · 79.6 MW · in study
- Lotus Solar FarmSolar · 50.0 MW · built
- Chowchilla Solar ProjectSolar · 20.0 MW · built
- Spectrum Energy Storage 2Battery storage · 566 MW · withdrawn
- Delilah Energy Storage 2Battery storage · 300 MW · withdrawn
- TrigoSolar + storage · 230 MW · withdrawn
- IrrigosaSolar + storage · 230 MW · withdrawn
- Madera Solar PV I (Fka Wheeler Ridge Solar PV1)Solar · 220 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem