SOLAR Β· CAISOPlacer Solar PV I
Placer Solar PV I is a 220 MW solar request withdrawn in the CAISO interconnection queue, in Placer County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2010 (completed)
- Withdrawn / abandonedMay 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 643F
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Rio Oso-Lockford 230 kV
- Location
- Placer County, California
- Technology
- Solar: 220 MW
- Total requested
- 220 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 July 2010
- Proposed online date
- March 2014
- Withdrawn
- May 2013
Location
Marker shows the centre of Placer County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Placer County
- Osito EnergySolar + storage Β· 613 MW Β· withdrawn
- Timber Energy StorageBattery storage Β· 214 MW Β· withdrawn
- Rocklin PeakerGas Β· 117 MW Β· withdrawn
- Meadows Energy StorageBattery storage Β· 102 MW Β· withdrawn
- Riosa Central SolarSolar Β· 20.2 MW Β· withdrawn
- Pleasant Grove Grid Stabilization ProjectBattery storage Β· 20.0 MW Β· withdrawn
- Lake Clementine HydroelectricHydro Β· 15.5 MW Β· withdrawn
- Lake Clementine Hydroelectric C7Hydro Β· 15.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem