United States βΊ Grid βΊ Interconnection queues βΊ California
SOLAR Β· CAISORiosa Central Solar
Riosa Central Solar is a 20.2 MW solar request withdrawn in the CAISO interconnection queue, in Placer County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedMar 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1361
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Smartville-Camp Far West 60kV line
- Location
- Placer County, California
- Technology
- Solar: 20.2 MW
- Total requested
- 20.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 1 May 2017
- Proposed online date
- November 2020
- Withdrawn
- March 2018
Location
Marker shows the centre of Placer County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Placer County
- Osito EnergySolar + storage Β· 613 MW Β· withdrawn
- Placer Solar PV ISolar Β· 220 MW Β· withdrawn
- Timber Energy StorageBattery storage Β· 214 MW Β· withdrawn
- Rocklin PeakerGas Β· 117 MW Β· withdrawn
- Meadows Energy StorageBattery storage Β· 102 MW Β· withdrawn
- Pleasant Grove Grid Stabilization ProjectBattery storage Β· 20.0 MW Β· withdrawn
- Lake Clementine HydroelectricHydro Β· 15.5 MW Β· withdrawn
- Lake Clementine Hydroelectric C7Hydro Β· 15.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem