Mojavalon I

Mojavalon I is a 146 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandonedApr 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
603
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Whirlwind Substation 230kV
Location
Kern County, California
Technology
Solar: 146 MW
Total requested
146 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
1 February 2010
Proposed online date
July 2013
Withdrawn
April 2010

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.