Interconnection queue in West (non-ISO utilities) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 9 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 667, Elmore County
Solar + storage · Martha Fields Energy Center, LLC
400 MWPaused / redesign Elmore, IDWest Aug 2022target 2029
Battery storage project Company 226, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project 665, Ada County
Solar + storage · Blacks Creek Energy Center, LLC
400 MWAgreement signed Ada, IDWest Aug 2022target 2027
Solar + storage project G0900, Linn County
Solar + storage
400 MWIn study Linn, ORWest Jun 2023target 2030
Battery storage project Company 206, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Solar project G0651, Lake County
Solar
400 MWIn study Lake, ORWest Jul 2020target 2023
Solar + storage project G0910, Deschutes County
Solar + storage
400 MWIn study Deschutes, ORWest Jul 2023target 2030
Solar + storage project IA-PNM-2020-04, Bernalillo County
Solar + storage
400 MWAgreement signed Bernalillo, NMWest Jan 2020target 2023
Other project G0904, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project C3-041, Harney County
Solar + storage · Lone Pine Energy, LLC
400 MWPaused / redesign Harney, ORWest May 2023target 2026
Battery storage project 25-00386, Storey County
Battery storage
400 MWIn study Storey, NVWest Jul 2025target 2031
Other project G0899, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project Company LX, Mineral County
Solar + storage
400 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Solar + storage project G0732, Benton County
Solar + storage
400 MWIn study Benton, WAWest Mar 2022target 2027
Other project G0902, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project Company JI, Washoe County
Solar + storage
400 MWAgreement signed Washoe, NVWest Sep 2018target 2023
Solar + storage project G0912, Deschutes County
Solar + storage
400 MWIn study Deschutes, ORWest Jul 2023target 2033
Solar + storage project G0747, Klamath County
Solar + storage
400 MWIn study Klamath, ORWest Jun 2022target 2026
Other project G0905, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0894, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project G0714, Sherman County
Solar + storage
400 MWIn study Sherman, ORWest Dec 2021target 2025
Solar project GI-2025-09, Cheyenne County
Solar
400 MWIn study Cheyenne, COWest Apr 2025target 2029
Other project G0892, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Battery storage project G0609, Multnomah County
Battery storage
400 MWIn study Multnomah, ORWest Dec 2018target 2021
Solar + storage project Q480, Navajo County
Solar + storage
400 MWIn study Navajo, AZWest Sep 2022target 2025
Solar project 5RSC-2024-21, Crowley County
Solar
400 MWIn study Crowley, COWest Jan 2024target 2029
Battery storage project G0862, Sherman County
Battery storage
400 MWIn study Sherman, ORWest May 2023target 2027
Solar + storage project Company OU, Lander County
Solar + storage
400 MWPaused / redesign Lander, NVWest Jan 2023target 2027
Solar + storage project G0909, Deschutes County
Solar + storage
400 MWIn study Deschutes, ORWest Jul 2023target 2028
Onshore wind project GI-TC-2024-16, Laramie County
Onshore wind
400 MWAgreement signed Laramie, WYWest May 2023target 2029
Solar + storage project G0820, Douglas County
Solar + storage
400 MWIn study Douglas, WAWest Nov 2022target 2027
Solar + storage project T2-076, Utah County
Solar + storage
400 MWIn study Utah, UTWest Sep 2025target 2027
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
Battery storage project T2-083, Emery County
Battery storage
400 MWIn study Emery, UTWest Sep 2025target 2030
Solar + storage project GI-2025-08, El Paso County
Solar + storage
400 MWIn study El Paso, COWest Apr 2025target 2029
Onshore wind project IA-PNM-2025-19, Torrance County
Onshore wind
400 MWIn study Torrance, NMWest Mar 2025target 2028
Solar + storage project C1-50, Utah County
Solar + storage · Mosida Solar, LLC
400 MWPaused / redesign Utah, UTWest May 2021target 2024
Onshore wind project G0956, Benewah County
Onshore wind
400 MWIn study Benewah, IDWest Oct 2023target 2026
Onshore wind project 836, Carbon County
Onshore wind · PacifiCorp
400 MWAgreement signed Carbon, WYWest Dec 2016target 2027
Va400B
Battery storage
400 MWIn study Dona Ana, NMWest Jun 2025target 2028
Solar + storage project T2-031, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-087, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-030, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project T2-086, Morrow County
Solar + storage · PacifiCorp
400 MWIn study Morrow, ORWest Sep 2025target 2028
Solar + storage project GI-TC-2024-30, Morgan County
Solar + storage
400 MWAgreement signed Morgan, COWest May 2024target 2028
Gas project Q2403, Maricopa County
Gas
398 MWIn study Maricopa, AZWest Feb 2024target 2028
Solar + storage project GI-TC-2024-31, Elbert County
Solar + storage
398 MWIn study Elbert, COWest May 2024target 2028
Solar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage
398 MWAgreement signed Prowers, COWest May 2022target 2029
Solar + storage project T2-029, Bingham County
Solar + storage · PacifiCorp
398 MWIn study Bingham, IDWest Sep 2025target 2028
Solar + storage project GI-DISIS-2021-10, Converse County
Solar + storage
398 MWPaused / redesign Converse, WYWest May 2021target 2023
Page 9 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)