United States › Grid › Interconnection queues › Colorado
SOLAR + STORAGE · WESTSolar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage project GI-DISIS-2022-13, Prowers County is a 398 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Prowers County, Colorado, connecting to Tri-State Generation and Transmission Association.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget May 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-DISIS-2022-13
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Lamar 230kV Substation
- Location
- Prowers County, Colorado
- Technology
- Solar: 199 MW · Battery: 199 MW
- Total requested
- 398 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed LGIA
- Queue status
- Active
- Entered queue
- 27 May 2022
- Proposed online date
- May 2029
Location
Marker shows the centre of Prowers County; the queue data does not give exact sites.
Other requests in Prowers County
- Onshore wind project GI-2006-1h, Prowers CountyOnshore wind · 75.0 MW · agreement signed
- Onshore wind project 5RSC-2024-18, Prowers CountyOnshore wind · 293 MW · in study
- Solar + storage project GI-CS-2025-28, Prowers CountySolar + storage · 110 MW · in study
- Solar + storage project GI-DISIS-2022-49, Prowers CountySolar + storage · 225 MW · suspended
- Onshore wind project GI-DISIS-2021-07, Prowers CountyOnshore wind · 199 MW · suspended
- Onshore wind project GI-2008-19, Prowers CountyOnshore wind · 500 MW · withdrawn
- Solar project GEN-2021-074, Prowers CountySolar · 500 MW · withdrawn
- Onshore wind project GEN-2021-046, Prowers CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project GI-2017-40, Prowers CountyOnshore wind · 302 MW · withdrawn
- Onshore wind project GI-2004-4, Prowers CountyOnshore wind · 280 MW · withdrawn
- Onshore wind project GI-2005-1, Prowers CountyOnshore wind · 279 MW · withdrawn
- Onshore wind project GI-2012-4, Prowers CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem