United States βΊ Grid βΊ Interconnection queues βΊ Colorado
ONSHORE WIND Β· WESTOnshore wind project GI-2008-19, Prowers County
Onshore wind project GI-2008-19, Prowers County is a 500 MW onshore wind request withdrawn in the West interconnection queue, in Prowers County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2008 (completed)
- Withdrawn / abandonedFeb 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2008-19
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Lamar Substation
- Location
- Prowers County, Colorado
- Technology
- Wind: 500 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study underway Request Withdrawn 2/1/13
- Queue status
- Withdrawn
- Entered queue
- 8 September 2008
- Proposed online date
- December 2011
- Withdrawn
- February 2013
Location
Marker shows the centre of Prowers County; the queue data does not give exact sites.
Other requests in Prowers County
- Solar + storage project GI-DISIS-2022-13, Prowers CountySolar + storage Β· 398 MW Β· agreement signed
- Onshore wind project GI-2006-1h, Prowers CountyOnshore wind Β· 75.0 MW Β· agreement signed
- Onshore wind project 5RSC-2024-18, Prowers CountyOnshore wind Β· 293 MW Β· in study
- Solar + storage project GI-CS-2025-28, Prowers CountySolar + storage Β· 110 MW Β· in study
- Solar + storage project GI-DISIS-2022-49, Prowers CountySolar + storage Β· 225 MW Β· suspended
- Onshore wind project GI-DISIS-2021-07, Prowers CountyOnshore wind Β· 199 MW Β· suspended
- Solar project GEN-2021-074, Prowers CountySolar Β· 500 MW Β· withdrawn
- Onshore wind project GEN-2021-046, Prowers CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project GI-2017-40, Prowers CountyOnshore wind Β· 302 MW Β· withdrawn
- Onshore wind project GI-2004-4, Prowers CountyOnshore wind Β· 280 MW Β· withdrawn
- Onshore wind project GI-2005-1, Prowers CountyOnshore wind Β· 279 MW Β· withdrawn
- Onshore wind project GI-2012-4, Prowers CountyOnshore wind Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem