United States › Grid › Interconnection queues › Oregon
SOLAR + STORAGE · WESTSolar + storage project G0910, Deschutes County
Solar + storage project G0910, Deschutes County is a 400 MW solar + storage request in interconnection study in the West interconnection queue, in Deschutes County, Oregon.
Queue statusIn planning
- PlanningQueued Jul 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0910
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- LaPine Substation
- Location
- Deschutes County, Oregon
- Technology
- Solar: 200 MW · Battery: 200 MW
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 18 July 2023
- Proposed online date
- November 2030
Location
Marker shows the centre of Deschutes County; the queue data does not give exact sites.
Other requests in Deschutes County
- Solar project G0539, Deschutes CountySolar · 600 MW · agreement signed
- Solar + storage project G1052, Deschutes CountySolar + storage · 2,600 MW · in study
- Solar + storage project G1051, Deschutes CountySolar + storage · 2,600 MW · in study
- Solar + storage project G1050, Deschutes CountySolar + storage · 1,300 MW · in study
- Battery storage project G1056, Deschutes CountyBattery storage · 650 MW · in study
- Onshore wind project G0861, Deschutes CountyOnshore wind · 500 MW · in study
- Solar + storage project G0912, Deschutes CountySolar + storage · 400 MW · in study
- Solar + storage project G0909, Deschutes CountySolar + storage · 400 MW · in study
- Geothermal project G1078, Deschutes CountyGeothermal · 54.0 MW · in study
- Solar project G1071, Deschutes CountySolar · 1.0 MW · in study
- Solar project T2-089, Deschutes CountySolar · 0.4 MW · in study
- Solar project 580, Deschutes CountySolar · 10.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem