Geothermal project G1078, Deschutes County

Geothermal project G1078, Deschutes County is a 54.0 MW geothermal request in interconnection study in the West interconnection queue, in Deschutes County, Oregon.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G1078
Grid region
West (non-ISO utilities)
Location
Deschutes County, Oregon
Technology
Geothermal: 54.0 MW
Total requested
54.0 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
23 June 2025
Proposed online date
July 2030

Location

Marker shows the centre of Deschutes County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Deschutes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem