United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 82

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 82 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2017-17, Elbert County
Onshore wind
300 MWWithdrawn / abandoned Elbert, COWest Jun 2017target 2020
Solar
Solar
300 MWWithdrawn / abandoned Aroostook, MEISO-NE Mar 2022target 2026
Battery storage project Company JA, Washoe County
Battery storage
300 MWWithdrawn / abandoned Washoe, NVWest Sep 2018target 2020
Solar + storage project C2-38, Sweetwater County
Solar + storage
300 MWWithdrawn / abandoned Sweetwater, WYWest Apr 2022target 2025
Solar project GI-75, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Other project G194 CONS 7, Saginaw County
Other
300 MWWithdrawn / abandoned Saginaw, MIMISO Nov 1998target 2005
Solar + storage project Company JU, Eureka County
Solar + storage
300 MWWithdrawn / abandoned Eureka, NVWest Mar 2019target 2023
Solar project J3802, Phillips County
Solar
300 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Onshore wind project J827, Fountain County
Onshore wind
300 MWWithdrawn / abandoned Fountain, INMISO Jun 2017target 2020
Onshore wind project GEN-2008-084, Oldham County
Onshore wind
300 MWWithdrawn / abandoned Oldham, TXSPP Aug 2008target 2011
Solar + storage project T2-090, Bannock County
Solar + storage
300 MWWithdrawn / abandoned Bannock, IDWest Sep 2025target 2027
Solar project GEN-2022-198, Lancaster County
Solar
300 MWWithdrawn / abandoned Lancaster, NESPP Feb 2023target 2028
Solar + storage project C2-36, Utah County
Solar + storage
300 MWWithdrawn / abandoned Utah, UTWest Apr 2022target 2025
Onshore wind project G0324, Garfield County
Onshore wind
300 MWWithdrawn / abandoned Garfield, WAWest Apr 2008target 2010
Onshore wind project 234, Umatilla County
Onshore wind · WKN Chopin, LLC
300 MWWithdrawn / abandoned Umatilla, ORWest Jul 2008
oyster shore III
Battery storage · Juno Power Management
300 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2022
Fort McKavett Wind
Onshore wind · Nextera
300 MWWithdrawn / abandoned Menard, TXERCOT Aug 2018target 2020
Solar project J2225, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Swan ESS
Battery storage
300 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2025
Onshore wind project GEN-2008-091, Grant County
Onshore wind
300 MWWithdrawn / abandoned Grant, OKSPP Aug 2008target 2011
Battery storage project J4162, Stearns County
Battery storage
300 MWWithdrawn / abandoned Stearns, MNMISO Sep 2025target 2028
Mavericks
Battery storage
300 MWWithdrawn / abandoned Alameda, CACAISO Apr 2018target 2021
Gas project R39, Middlesex County
Gas
300 MWWithdrawn / abandoned Middlesex, NJPJM Nov 2006target 2009
Plateau Solar
Solar · Innovative Solar 206, LLC
300 MWWithdrawn / abandoned ERCOT Dec 2019target 2025
Solar project G0630, Deer Lodge County
Solar
300 MWWithdrawn / abandoned Deer Lodge, MTWest Oct 2019target 2022
Stone Ranch Wind
Onshore wind · Iberdrola Renewables
300 MWWithdrawn / abandoned ERCOT Jul 2008target 2050
Solar project GEN-2017-207, Grant County
Solar
300 MWWithdrawn / abandoned Grant, OKSPP Nov 2017target 2021
Lazy J Solar
Solar · ConnectGen Operating LLC
300 MWWithdrawn / abandoned Leon, TXERCOT Jul 2019target 2021
Tremont BESS
Battery storage · Juno Power Management LLC
300 MWWithdrawn / abandoned Bronx, NYNYISO Aug 2020
Solar project J1885, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Onshore wind project GEN-2008-123, Dewey County
Onshore wind
300 MWWithdrawn / abandoned Dewey, OKSPP Nov 2008target 2010
Onshore wind project C4-018, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2024target 2028
Onshore wind project G796, Dodge County
Onshore wind
300 MWWithdrawn / abandoned Dodge, MNMISO May 2007target 2007
Solar project J2246, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Ruland Energy
Other · PP&L Global, Inc.
300 MWWithdrawn / abandoned NYNYISO Feb 2000
Onshore wind project G0323, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, ORWest Apr 2008target 2011
Solar project Q233, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Onshore wind project J2038, Montgomery County
Onshore wind
300 MWWithdrawn / abandoned Montgomery, INMISO Aug 2021target 2024
Battery storage project J3690, Scott County
Battery storage
300 MWWithdrawn / abandoned Scott, MOMISO Apr 2024target 2028
LSP Oakland
Gas
300 MWWithdrawn / abandoned Alameda, CACAISO Dec 2006target 2012
Alamitos Energy Storage
Battery storage
300 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2014target 2018
Solar + storage project C1-59, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest May 2021target 2024
Solar project 572, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest Nov 2019
Battery storage project G0938, Benton County
Battery storage
300 MWWithdrawn / abandoned Benton, WAWest Sep 2023target 2027
Solar project GEN-2023-239, Potter County
Solar
300 MWWithdrawn / abandoned Potter, TXSPP Oct 2023target 2030
East Setauket Energy Storage II
Battery storage · East Setauket energy Storage, LLC
300 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2023
Onshore wind project R63, Calhoun County
Onshore wind
300 MWWithdrawn / abandoned Calhoun, IAMISO Apr 2009target 2010
Solar project J3269, Hamilton County
Solar
300 MWWithdrawn / abandoned Hamilton, ILMISO Apr 2024target 2027
Solar + storage project C3-124, Juab County
Solar + storage
300 MWWithdrawn / abandoned Juab, UTWest May 2023target 2027
Onshore wind project C3-104, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Page 82 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)