United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project R63, Calhoun County

Onshore wind project R63, Calhoun County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Calhoun County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2009 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. ConsentedFeb 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R63
Grid region
MISO (Midcontinent)
Connection point (POI)
Raun - Lehigh 345 kV
Location
Calhoun County, Iowa
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
8 April 2009
Agreement signed
15 February 2012
Proposed online date
December 2010
Withdrawn
February 2012

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Calhoun County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem