SOLAR + STORAGE Β· WEST

Solar + storage project C2-36, Utah County

Solar + storage project C2-36, Utah County is a 300 MW solar + storage request withdrawn in the West interconnection queue, in Utah County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-36
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Mercer substation
Location
Utah County, Utah
Technology
Solar: 300 MW Β· Battery
Total requested
300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
28 April 2022
Proposed online date
December 2025

Location

Marker shows the centre of Utah County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Utah County