United States › Grid › Interconnection queues › Ohio

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Ohio — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown59480.2 GW
Active in queue19.7 GW185 requests
Agreement signed8,251 MW65 requests
Withdrawn59480.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

594 requests · page 8 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AD1-141, Scioto County
Solar
50.0 MWWithdrawn / abandoned Scioto, OHPJM Sep 2017target 2019
Stone Branch Solar
Solar
49.9 MWWithdrawn / abandoned Adams, OHPJM Apr 2016target 2023
Solar project AG1-068, Adams County
Solar
49.9 MWWithdrawn / abandoned Adams, OHPJM Jul 2020target 2023
Cardinal Solar
Solar
49.9 MWWithdrawn / abandoned Union, OHPJM Mar 2019target 2023
Solar + storage project AH2-284, Adams County
Solar + storage
49.9 MWWithdrawn / abandoned Adams, OHPJM Mar 2022target 2026
Norwalk Solar I
Solar + storage · Norwalk Solar, LLC
49.9 MWWithdrawn / abandoned Huron, OHPJM Jul 2021target 2025
Solar project AE2-302, Jackson County
Solar
49.9 MWWithdrawn / abandoned Jackson, OHPJM Mar 2019target 2022
Solar project AG2-218, Marion County
Solar
49.5 MWWithdrawn / abandoned Marion, OHPJM Mar 2021target 2024
Solar project AG2-691, Montgomery County
Solar
49.5 MWWithdrawn / abandoned Montgomery, OHPJM Mar 2021target 2025
Solar project AH1-608, Richland County
Solar
49.3 MWWithdrawn / abandoned Richland, OHPJM Sep 2021target 2025
Solar project AF1-230, Crawford County
Solar
49.0 MWWithdrawn / abandoned Crawford, OHPJM Sep 2019target 2022
Solar project AC2-040, Highland County
Solar
49.0 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Solar + storage project AG2-333, Fayette County
Solar + storage
49.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Solar project AD2-012, Highland County
Solar
49.0 MWWithdrawn / abandoned Highland, OHPJM Nov 2017target 2019
Solar project AF2-123, Madison County
Solar
49.0 MWWithdrawn / abandoned Madison, OHPJM Feb 2020target 2023
Solar project AC2-035, Jackson County
Solar
49.0 MWWithdrawn / abandoned Jackson, OHPJM Feb 2017target 2019
Solar project AC2-049, Highland County
Solar
49.0 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Paulding aka Project R48
Onshore wind
48.3 MWWithdrawn / abandoned Paulding, OHPJM Dec 2006target 2020
Onshore wind project G652, Erie County
Onshore wind
48.0 MWWithdrawn / abandoned Erie, OHMISO Jul 2006target 2008
Onshore wind project R51, Champaign County
Onshore wind
48.0 MWWithdrawn / abandoned Champaign, OHPJM Dec 2006target 2010
Solar project AH1-333, Butler County
Solar
48.0 MWWithdrawn / abandoned Butler, OHPJM Sep 2021target 2024
Onshore wind project R50, Logan County
Onshore wind
48.0 MWWithdrawn / abandoned Logan, OHPJM Dec 2006target 2009
Onshore wind project O21, Logan County
Onshore wind
48.0 MWWithdrawn / abandoned Logan, OHPJM May 2005target 2008
Solar project AC2-055, Highland County
Solar
47.5 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Solar project AH1-522, Paulding County
Solar
47.0 MWWithdrawn / abandoned Paulding, OHPJM Sep 2021target 2024
Solar project AC1-210, Madison County
Solar
45.0 MWWithdrawn / abandoned Madison, OHPJM Oct 2016target 2018
Solar project AF2-186, Paulding County
Solar
45.0 MWWithdrawn / abandoned Paulding, OHPJM Mar 2020target 2023
Solar project AC2-039, Athens County
Solar
43.0 MWWithdrawn / abandoned Athens, OHPJM Feb 2017target 2019
Solar project AH1-569, Union County
Solar · Glacier Ridge Solar, LLC
42.0 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Battery storage project AH1-483, Union County
Battery storage
42.0 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Solar project AF2-084, Union County
Solar
42.0 MWWithdrawn / abandoned Union, OHPJM Jan 2020target 2022
Other project G071, Greene County
Other
41.0 MWWithdrawn / abandoned Greene, OHMISO Jan 2001target 2006
Solar + storage project AI1-098, Pickaway County
Solar + storage
40.0 MWWithdrawn / abandoned Pickaway, OHPJM Aug 2022target 2026
Solar + storage project AG2-263, Fayette County
Solar + storage
40.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Bellefontaine PV and BESS Project
Solar + storage · Hodson GreenDefine Blue Jacket LLC
40.0 MWWithdrawn / abandoned Logan, OHPJM Sep 2020target 2023
Solar project AB2-064, Van Wert County
Solar
40.0 MWWithdrawn / abandoned Van Wert, OHPJM Mar 2016target 2018
Onshore wind project T48, Mercer County
Onshore wind
40.0 MWWithdrawn / abandoned Mercer, OHPJM Sep 2007target 2013
Solar project AG2-663, Columbiana County
Solar
40.0 MWWithdrawn / abandoned Columbiana, OHPJM Mar 2021target 2025
Solar project AB2-103, Adams County
Solar
40.0 MWWithdrawn / abandoned Adams, OHPJM Apr 2016target 2017
Coal project AD2-078, Scioto County
Coal
40.0 MWWithdrawn / abandoned Scioto, OHPJM Mar 2018target 2020
Solar project AH1-404, Highland County
Solar
40.0 MWWithdrawn / abandoned Highland, OHPJM Sep 2021target 2024
Solar project AB2-083, Ross County
Solar
40.0 MWWithdrawn / abandoned Ross, OHPJM Apr 2016target 2017
Solar + storage project AG2-277, Fayette County
Solar + storage
40.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Solar + storage project AH1-421, Champaign County
Solar + storage
40.0 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Solar + storage project AH1-614, Clermont County
Solar + storage
40.0 MWWithdrawn / abandoned Clermont, OHPJM Sep 2021target 2025
Solar project AH1-058, Morrow County
Solar
40.0 MWWithdrawn / abandoned Morrow, OHPJM Jul 2021target 2024
Solar project AF2-067, Preble County
Solar
40.0 MWWithdrawn / abandoned Preble, OHPJM Jan 2020target 2022
Gas project J127, Wood County
Gas
40.0 MWWithdrawn / abandoned Wood, OHMISO Apr 2010
Solar + storage project AH1-219, Logan County
Solar + storage
39.9 MWWithdrawn / abandoned Logan, OHPJM Sep 2021target 2025
Solar project AF2-127, Defiance County
Solar
38.0 MWWithdrawn / abandoned Defiance, OHPJM Feb 2020target 2022
Page 8 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)