Solar project AG2-663, Columbiana County

Solar project AG2-663, Columbiana County is a 40.0 MW solar request withdrawn in the PJM interconnection queue, in Columbiana County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-663
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Pidgeon - Lisbon 69 kV
Location
Columbiana County, Ohio
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
July 2025
Withdrawn
August 2022

Location

Marker shows the centre of Columbiana County; the queue data does not give exact sites.