United States › Grid › Interconnection queues › Ohio
COAL · MISOCoal project G689, Columbiana County
Coal project G689, Columbiana County is a 560 MW coal request built and operating in the MISO interconnection queue, in Columbiana County, Ohio.
Request details
- Queue ID
- G689
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 345 kV line near Sammis Plant near Wellsville, OH
- Location
- Columbiana County, Ohio
- Technology
- Coal: 560 MW
- Total requested
- 560 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 12 October 2006
- Agreement signed
- 31 August 2010
- Proposed online date
- October 2008
- Came online
- October 2008
Location
Marker shows the centre of Columbiana County; the queue data does not give exact sites.
Other requests in Columbiana County
- Gas project AH1-699, Columbiana CountyGas · 69.0 MW · in study
- Gas project AH2-106, Columbiana CountyGas · 69.0 MW · in study
- Kensington SolarSolar · 145 MW · suspended
- South Field Energy Power PlantGas · 1,152 MW · built
- Coal project R13, Columbiana CountyCoal · 350 MW · withdrawn
- Solar project AG2-663, Columbiana CountySolar · 40.0 MW · withdrawn
- Gas project AB1-178, Columbiana CountyGas · 19.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem