SOLAR + STORAGE · PJMBellefontaine PV and BESS Project
Bellefontaine PV and BESS Project is a 40.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Logan County, Ohio, connecting to Dayton.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-323
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Developer
- Hodson GreenDefine Blue Jacket LLC
- Connection point (POI)
- Blue Jacket 138 kV
- Location
- Logan County, Ohio
- Technology
- Solar: 40.0 MW · Battery
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- September 2023
- Withdrawn
- November 2025
Location
Marker shows the centre of Logan County; the queue data does not give exact sites.
Other requests in Logan County
- Solar project AI2-081, Logan CountySolar · 271 MW · in study
- Solar project AH2-010, Logan CountySolar · 100 MW · in study
- Cherokee Run LFOther · 10.0 MW · built
- Grange SolarSolar · 500 MW · withdrawn
- Grange SolarSolar + storage · 400 MW · withdrawn
- Grange SolarBattery storage · 200 MW · withdrawn
- Solar project AG2-013, Logan CountySolar · 200 MW · withdrawn
- Solar + storage project AH2-147, Logan CountySolar + storage · 119 MW · withdrawn
- Onshore wind project G756, Logan CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project S51, Logan CountyOnshore wind · 99.0 MW · withdrawn
- Battery storage project AH1-320, Logan CountyBattery storage · 69.0 MW · withdrawn
- Solar project AH1-198, Logan CountySolar · 55.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem