πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR Β· PJM

Stone Branch Solar

Stone Branch Solar is a 49.9 MW solar request withdrawn in the PJM interconnection queue, in Adams County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. ConsentedNov 2021 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-085
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Adams 138kV
Location
Adams County, Ohio
Technology
Solar: 49.9 MW
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
18 April 2016
Agreement signed
1 November 2021
Proposed online date
December 2023
Withdrawn
March 2025

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem