United States βΊ Grid βΊ Interconnection queues βΊ Ohio
OTHER Β· PJMOther project AD2-053, Adams County
Other project AD2-053, Adams County is a 50.0 MW other request withdrawn in the PJM interconnection queue, in Adams County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2018 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD2-053
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- South Canton-Harmon 345kV
- Location
- Adams County, Ohio
- Technology
- Other: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 2 February 2018
- Proposed online date
- June 2019
- Withdrawn
- September 2018
Location
Marker shows the centre of Adams County; the queue data does not give exact sites.
Other requests in Adams County
- Solar + storage project AH2-146, Adams CountySolar + storage Β· 87.2 MW Β· in study
- Solar project AI1-151, Adams CountySolar Β· 53.2 MW Β· in study
- Solar + storage project AI2-030, Adams CountySolar + storage Β· 50.0 MW Β· in study
- Gavin 2Coal Β· 20.0 MW Β· built
- Gavin 1Coal Β· 20.0 MW Β· built
- Killen Electric Generating StationCoal Β· 12.0 MW Β· built
- Stuart Electric Generating StationCoal Β· 7.0 MW Β· built
- Coal project S12, Adams CountyCoal Β· 1,300 MW Β· withdrawn
- Battery storage project AH1-758, Adams CountyBattery storage Β· 500 MW Β· withdrawn
- Other project AE1-078, Adams CountyOther Β· 50.0 MW Β· withdrawn
- Stone Branch SolarSolar Β· 49.9 MW Β· withdrawn
- Solar project AG1-068, Adams CountySolar Β· 49.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem