πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OTHER Β· PJM

Other project AE1-078, Adams County

Other project AE1-078, Adams County is a 50.0 MW other request withdrawn in the PJM interconnection queue, in Adams County, Ohio, connecting to DEOK.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2018 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-078
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Greendale-Miami Fort 138kV Upgrades
Location
Adams County, Ohio
Technology
Other: 50.0 MW
Total requested
50.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: System Impact Study
Queue status
Withdrawn
Entered queue
7 August 2018
Proposed online date
June 2020
Withdrawn
September 2019

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem