United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR + STORAGE Β· PJM

Solar + storage project AH2-284, Adams County

Solar + storage project AH2-284, Adams County is a 49.9 MW solar + storage request withdrawn in the PJM interconnection queue, in Adams County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-284
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Adams 138 kV
Location
Adams County, Ohio
Technology
Solar: 49.9 MW Β· Battery
Total requested
49.9 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 March 2022
Proposed online date
December 2026
Withdrawn
December 2024

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem