Requests shown66688.2 GW
Active in queue7,680 MW38 requests
Agreement signed4,576 MW30 requests
Withdrawn66688.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

666 requests ยท page 7 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 437, Elmore County
Solar
70.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar project IC-344, Glynn County
Solar
70.0 MWWithdrawn / abandoned Glynn, GASoutheast Mar 2014
Solar project IC-355, Taylor County
Solar
70.0 MWWithdrawn / abandoned Taylor, GASoutheast Apr 2014
Garrett County Wind Facility
Onshore wind
69.1 MWWithdrawn / abandoned Garrett, MDPJM Aug 2014target 2018
Solar project 260, Lake County
Solar
68.0 MWWithdrawn / abandoned Lake, TNSoutheast Nov 2014
Onshore wind project AA1-113, Schuylkill County
Onshore wind
68.0 MWWithdrawn / abandoned Schuylkill, PAPJM Oct 2014target 2017
Onshore wind project Z2-101, Schuylkill County
Onshore wind
67.5 MWWithdrawn / abandoned Schuylkill, PAPJM Apr 2014target 2016
Solar project 250, Monroe County
Solar
67.0 MWWithdrawn / abandoned Monroe, MSSoutheast Jul 2014
Solar project 252, Monroe County
Solar
67.0 MWWithdrawn / abandoned Monroe, MSSoutheast Jul 2014
Sunshine Valley Solar 3
Solar
65.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2017
Other project AA1-120
Other
64.0 MWWithdrawn / abandoned PJM Oct 2014
Solar project BHCT G13, Pueblo County
Solar
63.0 MWWithdrawn / abandoned Pueblo, COWest Sep 2014target 2017
Wind + storage project 170, Big Horn County
Wind + storage
62.5 MWWithdrawn / abandoned Big Horn, MTWest Jul 2014target 2016
Mason Mt Wind
Onshore wind ยท Enel Green
62.0 MWWithdrawn / abandoned ERCOT Apr 2014target 2019
Solar project IC-380, Twiggs County
Solar
60.0 MWWithdrawn / abandoned Twiggs, GASoutheast May 2014
Gas project GEN-2014-027, Okfuskee County
Gas
60.0 MWWithdrawn / abandoned Okfuskee, OKSPP Sep 2014target 2016
East Hampton Solar
Solar ยท East Hampton Solar Farm, LLC
60.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2014
Pandora Solar
Solar
60.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2014target 2018
Shawboro East Ridge Solar Park
Solar
60.0 MWWithdrawn / abandoned Currituck, NCPJM Oct 2014target 2015
Other project AA1-035
Other
60.0 MWWithdrawn / abandoned PJM Aug 2014
Gas project 173, Lewis And Clark County
Gas
60.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Sep 2014target 2014
Solar project GI-2014-8, Pueblo County
Solar
60.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2014target 2016
Solar project BHCT-G12, Pueblo County
Solar ยท Black Hills Electric Generation LLC
60.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2014target 2016
Onshore wind project AA1-114, Carbon County
Onshore wind
60.0 MWWithdrawn / abandoned Carbon, PAPJM Oct 2014target 2017
Parker Ranch Solar 2
Solar ยท SunPower
56.0 MWWithdrawn / abandoned ERCOT Dec 2014target 2018
Solar project GI-2014-12, Pueblo County
Solar
53.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2014target 2016
Wind
Onshore wind
52.8 MWWithdrawn / abandoned Penobscot, MEISO-NE Aug 2014target 2017
M&G Resins Corpus Christi
Gas ยท M&G Resins USA, LLC
51.0 MWWithdrawn / abandoned ERCOT Jan 2014target 2015
Solar project Company 135, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2017
Solar project Q224, Maricopa County
Solar
50.0 MWWithdrawn / abandoned Maricopa, AZWest Sep 2014target 2016
Solar project 576, Salt Lake County
Solar
50.0 MWWithdrawn / abandoned Salt Lake, UTWest Jun 2014target 2015
Solar project GEN-2014-045, Grant County
Solar
50.0 MWWithdrawn / abandoned Grant, KSSPP Sep 2014target 2016
Solar project J341, Chisago County
Solar
50.0 MWWithdrawn / abandoned Chisago, MNMISO May 2014
SGS Fremont
Battery storage
50.0 MWWithdrawn / abandoned Alameda, CACAISO Apr 2014target 2019
Solar project J350, Chicot County
Solar
50.0 MWWithdrawn / abandoned Chicot, ARMISO May 2014
SKY Valley Wind
Onshore wind
50.0 MWWithdrawn / abandoned Solano, CACAISO Apr 2014target 2017
Solar project GEN-2014-042, Hockley County
Solar
50.0 MWWithdrawn / abandoned Hockley, TXSPP Sep 2014target 2016
Roadrunner
Solar
50.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2019
Solar project GEN-2014-044, Terry County
Solar
50.0 MWWithdrawn / abandoned Terry, TXSPP Sep 2014target 2016
BThorn
Solar ยท SunEdison
50.0 MWWithdrawn / abandoned ERCOT Nov 2014target 2020
SolaireHolman 2
Solar ยท Solaire Direct
50.0 MWWithdrawn / abandoned ERCOT Jun 2014target 2016
Solar project J428, Jefferson County
Solar
50.0 MWWithdrawn / abandoned Jefferson, TXMISO Nov 2014target 2018
Solar project J370, Jackson County
Solar
50.0 MWWithdrawn / abandoned Jackson, ARMISO Jun 2014
Solar project GEN-2014-036, Harmon County
Solar
50.0 MWWithdrawn / abandoned Harmon, OKSPP Sep 2014target 2016
Caballo Loco
Solar
50.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2019
Solar project Company 134, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2016
Solar project IC-377, Tattnall County
Solar
50.0 MWWithdrawn / abandoned Tattnall, GASoutheast May 2014
Solar project 590, Juab County
Solar
50.0 MWWithdrawn / abandoned Juab, UTWest Jul 2014target 2016
Rose Meadow Wind Bank
Battery storage
50.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2014target 2022
SGS Livermore (Fka SGS South San Francisco)
Battery storage
50.0 MWWithdrawn / abandoned San Mateo, CACAISO Apr 2014target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)