SOLAR Β· SPP

Solar project GEN-2014-036, Harmon County

Solar project GEN-2014-036, Harmon County is a 50.0 MW solar request withdrawn in the SPP interconnection queue, in Harmon County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandonedMar 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-036
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Hollis 138kV
Location
Harmon County, Oklahoma
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 September 2014
Proposed online date
December 2016
Withdrawn
March 2015

Location

Marker shows the centre of Harmon County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Harmon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem