ONSHORE WIND · PJM

Garrett County Wind Facility

Garrett County Wind Facility is a 69.1 MW onshore wind request withdrawn in the PJM interconnection queue, in Garrett County, Maryland, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2014 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA1-047
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Hazelton-Jennings 138kV
Location
Garrett County, Maryland
Technology
Wind: 69.1 MW
Total requested
69.1 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
29 August 2014
Proposed online date
December 2018
Withdrawn
January 2020

Location

Marker shows the centre of Garrett County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Garrett County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem