ONSHORE WIND · PJM

Fair Wind Project

Fair Wind Project is a 30.0 MW onshore wind request built and operating in the PJM interconnection queue, in Garrett County, Maryland, connecting to APS.

Queue statusOperating
  1. PlanningQueued Aug 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
T16
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Kelso Gap 138kV
Location
Garrett County, Maryland
Technology
Wind: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
20 August 2007
Proposed online date
October 2015
Came online
November 2015

Location

Marker shows the centre of Garrett County; the queue data does not give exact sites.