United States βΊ Grid βΊ Interconnection queues βΊ Maryland
SOLAR + STORAGE Β· PJMSolar + storage project AG1-078, Garrett County
Solar + storage project AG1-078, Garrett County is a 60.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Garrett County, Maryland, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2020 (completed)
- Withdrawn / abandonedAug 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-078
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Location
- Garrett County, Maryland
- Technology
- Solar: 60.0 MW Β· Battery
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 July 2020
- Proposed online date
- September 2023
- Withdrawn
- August 2020
Location
Marker shows the centre of Garrett County; the queue data does not give exact sites.
Other requests in Garrett County
- Jade Meadow III Solar FacilitySolar + storage Β· 300 MW Β· agreement signed
- CPV Backbone SolarSolar Β· 175 MW Β· agreement signed
- CPV Wilson SolarSolar Β· 200 MW Β· in study
- Kelso Gap WFOnshore wind Β· 100 MW Β· built
- Four Mile Ridge WF - 24 WTOnshore wind Β· 60.0 MW Β· built
- Roth Rock WFOnshore wind Β· 50.0 MW Β· built
- Fair Wind ProjectOnshore wind Β· 30.0 MW Β· built
- Kelso Gap WFOnshore wind Β· 20.0 MW Β· built
- Gas project D05_W17, Garrett CountyGas Β· 432 MW Β· withdrawn
- Garrett County Wind FacilityOnshore wind Β· 69.1 MW Β· withdrawn
- Winding Ridge Wind FarmOnshore wind Β· 60.0 MW Β· withdrawn
- Onshore wind project N29, Garrett CountyOnshore wind Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem