ONSHORE WIND Β· ISO-NE

Wind

Wind is a 52.8 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Penobscot County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2014 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
476
Grid region
ISO-NE (New England)
Connection point (POI)
Emera Maine (Bangor Hydro) Keene Road Substation (Connecting through Evergreen Gen Lead, LLC Line 56)
Location
Penobscot County, Maine
Technology
Wind: 52.8 MW
Total requested
52.8 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 August 2014
Proposed online date
October 2017
Withdrawn
June 2016

Location

Marker shows the centre of Penobscot County; the queue data does not give exact sites.