SOLAR Β· MISO

Solar project J341, Chisago County

Solar project J341, Chisago County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Chisago County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2014 (completed)
  2. Withdrawn / abandonedJan 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J341
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Chisago County, Minnesota
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
19 May 2014
Withdrawn
January 2016

Location

Marker shows the centre of Chisago County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Chisago County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem