United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in CAISO (California) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown429188.6 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

429 requests · page 7 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Tanager Storage
Battery storage
200 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2027
Avocet Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Conduit Energy Storage 2
Battery storage
199 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Buttercup Hybrid Solar
Solar + storage
197 MWIn study Merced, CACAISO Apr 2021target 2032
American Kings Solar
Solar + storage
197 MWAgreement signed Kings, CACAISO Nov 20072020
Lycan Solar 2
Solar
192 MWIn study Riverside, CACAISO Apr 2023target 2028
Sandrini Sol 1
Solar + storage
192 MWAgreement signed Kern, CACAISO May 2017target 2025
Redux Solar
Solar + storage
190 MWAgreement signed Fresno, CACAISO May 2017target 2026
Pastoria Solar
Solar + storage
187 MWAgreement signed Kern, CACAISO May 2016target 2026
Gaskell West
Solar + storage
187 MWAgreement signed Kern, CACAISO Apr 2014target 2026
Tracy Combined-Cycle Power Plant
Gas
185 MWAgreement signed San Joaquin, CACAISO Oct 20072012
Kettle Solar One
Solar + storage
180 MWAgreement signed San Diego, CACAISO Apr 2018target 2026
Black Diamond ES2
Battery storage
179 MWAgreement signed Contra Costa, CACAISO Apr 2021target 2031
Conaway Hybrid Power Plant
Solar + storage
170 MWIn study Yolo, CACAISO Apr 2020target 2023
Lockhart Solar 2
Solar + storage
165 MWAgreement signed San Bernardino, CACAISO Apr 2019target 2026
Janus
Solar + storage
164 MWAgreement signed Colusa, CACAISO Apr 2018target 2026
Hacienda
Solar
157 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Argenta
Solar
156 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Zeta
Solar + storage
155 MWAgreement signed Merced, CACAISO Apr 2020target 2027
Crystal Flats
Solar + storage
155 MWAgreement signed Kern, CACAISO Apr 2020target 2030
Zinfandel Storage Center
Battery storage
154 MWIn study San Joaquin, CACAISO Apr 2023target 2030
Bobor Storage
Battery storage
152 MWIn study Tulare, CACAISO Apr 2021target 2030
Flores Storage
Battery storage
152 MWIn study Madera, CACAISO Apr 2021target 2031
Sunrise Butte
Solar + storage
150 MWAgreement signed Imperial, CACAISO Apr 2019target 2029
Saloon Energy Storage
Battery storage
150 MWAgreement signed Colusa, CACAISO Apr 2018target 2027
Sandstorm Wind Power
Wind + storage
150 MWAgreement signed Riverside, CACAISO Oct 2006target 2030
Segs Expansion 2 Hybrid
Solar + storage
145 MWAgreement signed San Bernardino, CACAISO Apr 2020target 2026
Jasmine
Solar + storage
141 MWAgreement signed Kern, CACAISO Apr 2018target 2026
Alta Vista Suntower Generating Station
Solar + storage
132 MWAgreement signed Los Angeles, CACAISO Jan 20082013
Montezuma II
Wind + storage
132 MWAgreement signed Solano, CACAISO May 20072012
Reflex
Solar
129 MWIn study Riverside, CACAISO Apr 2023target 2029
Holly Oaks
Battery storage
128 MWIn study Calaveras, CACAISO Apr 2023target 2028
Leconte Energy Storage
Battery storage
125 MWAgreement signed Imperial, CACAISO Apr 2015target 2026
Saddle Mountain Solar
Solar
125 MWAgreement signed Maricopa, AZCAISO Apr 2020target 2025
Baldy Mesa 2
Solar + storage
125 MWAgreement signed San Bernardino, CACAISO Apr 2018target 2026
El Rey Power Bank
Battery storage
124 MWIn study Monterey, CACAISO Apr 2021target 2029
Ajo Power Bank
Battery storage
124 MWAgreement signed Santa Clara, CACAISO Apr 2018target 2028
Bonita Bateria 2
Battery storage
123 MWIn study Orange, CACAISO Apr 2023target 2029
Los Esteros Critical Energy Facility Expansion
Gas
123 MWAgreement signed Santa Clara, CACAISO May 2008target 2023
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
High Winds Storage
Battery storage
121 MWIn study Solano, CACAISO Apr 2021target 2031
Excelsior Solar (Fka: Burford Five Points)
Solar + storage
120 MWAgreement signed Fresno, CACAISO Mar 20112016
Gonzaga Hybrid
Wind + storage
115 MWAgreement signed Merced, CACAISO Apr 2020target 2026
Reclaimed Wind
Battery storage
114 MWAgreement signed Alameda, CACAISO Apr 2018target 2026
Serena Storage
Battery storage
114 MWAgreement signed Kern, CACAISO Apr 2021target 2029
Mulqueeney Ranch Wind
Onshore wind
114 MWAgreement signed Alameda, CACAISO May 2016target 2026
Sienna Solar 2
Solar + storage
112 MWIn study San Bernardino, CACAISO Apr 2021target 2029
Toland Renewable Energy Park
Onshore wind
108 MWIn study Solano, CACAISO Apr 2023target 2029
Voyager Energy Storage
Battery storage
105 MWIn study Kern, CACAISO Apr 2023target 2027
Ulua
Battery storage
105 MWIn study Los Angeles, CACAISO Apr 2023target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)