WIND + STORAGE · CAISO

Sandstorm Wind Power

Sandstorm Wind Power is a 150 MW wind + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Oct 2006 (completed)
  2. ConsentedOct 2014 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
138
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Devers Substation 220 kV
Location
Riverside County, California
Technology
Wind: 60.0 MW · Battery: 90.0 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
23 October 2006
Agreement signed
9 October 2014
Proposed online date
February 2030

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.