United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2017 requests) โ€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,258161.7 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,258 requests ยท page 6 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2017-021, Edwards County
Onshore wind
200 MWWithdrawn / abandoned Edwards, KSSPP May 20172023
Onshore wind project GEN-2017-032, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, COSPP May 20172023
Onshore wind project J714, Montgomery County
Onshore wind
200 MWWithdrawn / abandoned Montgomery, INMISO Jun 2017target 2019
Goldwick Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Stanislaus, CACAISO May 2017target 2020
Onshore wind project GEN-2017-098, Meade County
Onshore wind
200 MWWithdrawn / abandoned Meade, SDSPP May 2017target 2020
Solar project 988, Converse County
Solar
200 MWWithdrawn / abandoned Converse, WYWest Dec 2017target 2020
March Road Solar
Solar ยท Eon
200 MWWithdrawn / abandoned Tom Green, TXERCOT Nov 2017target 2021
Solar project GI-2017-27, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Onshore wind project J835, Morgan County
Onshore wind
200 MWWithdrawn / abandoned Morgan, ILMISO Jun 2017target 2020
Onshore wind project J726, Cottonwood County
Onshore wind
200 MWWithdrawn / abandoned Cottonwood, MNMISO Jun 2017target 2019
Onshore wind project GEN-2017-038, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP May 2017target 2020
Onshore wind project J632, Berrien County
Onshore wind
200 MWWithdrawn / abandoned Berrien, MIMISO Jun 2017target 2018
Solar project J946, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2020
Goodranch Solar
Solar ยท EDF Renewable Energy
200 MWWithdrawn / abandoned Borden, TXERCOT Jun 2017target 2021
Onshore wind project GEN-2017-041, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP May 2017target 2020
Onshore wind project GEN-2017-017, Thomas County
Onshore wind
200 MWWithdrawn / abandoned Thomas, KSSPP May 2017target 2020
Onshore wind project J842, Gibson County
Onshore wind
200 MWWithdrawn / abandoned Gibson, INMISO Jun 2017target 2022
Onshore wind project GEN-2017-112, Bates County
Onshore wind
200 MWWithdrawn / abandoned Bates, MOSPP Nov 20172024
Onshore wind project J933, Day County
Onshore wind
200 MWWithdrawn / abandoned Day, SDMISO Jun 2017target 2021
Onshore wind project J203, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Jun 2017target 2012
Solar project GEN-2017-174, Comanche County
Solar
200 MWWithdrawn / abandoned Comanche, OKSPP Nov 2017target 2020
Solar project J900, Livingston Parish County
Solar
200 MWWithdrawn / abandoned Livingston Parish, LAMISO Jun 2017target 2020
Solar project 980, Box Elder County
Solar
200 MWWithdrawn / abandoned Box Elder, UTWest Nov 2017target 2020
Onshore wind project J843, Gibson County
Onshore wind
200 MWWithdrawn / abandoned Gibson, INMISO Jun 2017target 2021
Onshore wind project GEN-2017-013, Thomas County
Onshore wind
200 MWWithdrawn / abandoned Thomas, KSSPP May 20172023
Onshore wind project J901, Redwood County
Onshore wind
200 MWWithdrawn / abandoned Redwood, MNMISO Jun 2017target 2021
Solar project IC-605, Mitchell County
Solar
200 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2017
Calhawk Solar Farm
Solar + storage
200 MWWithdrawn / abandoned Tulare, CACAISO May 2017target 2022
Solar project 324, Limestone County
Solar
200 MWWithdrawn / abandoned Limestone, ALSoutheast Aug 2017
Solar project AC2-042, Highland County
Solar
200 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Solar project AD2-010, Highland County
Solar
200 MWWithdrawn / abandoned Highland, OHPJM Nov 2017target 2019
Onshore wind project J725, Murray County
Onshore wind
200 MWWithdrawn / abandoned Murray, MNMISO Jun 2017target 2020
Onshore wind project J872, Macon County
Onshore wind
200 MWWithdrawn / abandoned Macon, ILMISO Jun 2017target 2020
Onshore wind project J943, Lincoln County
Onshore wind
200 MWWithdrawn / abandoned Lincoln, MNMISO Jun 2017target 2020
Solar project J945, Washington County
Solar
200 MWWithdrawn / abandoned Washington, MSMISO Jun 2017target 2019
Solar project GEN-2017-202, New Madrid County
Solar
200 MWWithdrawn / abandoned New Madrid, MOSPP Nov 2017target 2026
Onshore wind project J860, Jefferson Davis Parish County
Onshore wind
200 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Jun 2017target 2020
Solar project GEN-2017-088, Bowie County
Solar
200 MWWithdrawn / abandoned Bowie, TXSPP May 2017target 2020
Onshore wind project AC2-080, Jasper County
Onshore wind
200 MWWithdrawn / abandoned Jasper, INPJM Feb 2017target 2019
Onshore wind project J941, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, SDMISO Jun 2017target 2020
Solar project 851, Juab County
Solar
200 MWWithdrawn / abandoned Juab, UTWest Feb 2017target 2020
Gas project 324, Yellowstone County
Gas
200 MWWithdrawn / abandoned Yellowstone, MTWest Jul 2017target 2019
Solar project GI-2017-34, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2020
Onshore wind project GI-2017-42, Kiowa County
Onshore wind
200 MWWithdrawn / abandoned Kiowa, COWest Nov 2017target 2020
Solar project 987, Klamath County
Solar
200 MWWithdrawn / abandoned Klamath, ORWest Dec 2017target 2020
Onshore wind project GEN-2017-095, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP May 2017target 2020
Solar project Company HY, Lander County
Solar
200 MWWithdrawn / abandoned Lander, NVWest Sep 2017target 2019
Onshore wind project J743, Cass County
Onshore wind
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2017target 2020
Onshore wind project J310, Dodge County
Onshore wind
200 MWWithdrawn / abandoned Dodge, MNMISO Jun 2017target 2017
Solar project 53, Thurston County
Solar
198 MWWithdrawn / abandoned Thurston, WAWest Oct 2017target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)