United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-021, Edwards County

Onshore wind project GEN-2017-021, Edwards County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Edwards County, Kansas, connecting to ITCGP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedJun 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingNov 2023 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-021
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Post Rock - Spearville 345 kV
Location
Edwards County, Kansas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 May 2017
Proposed online date
November 2023
Came online
November 2023
Withdrawn
June 2022

Location

Marker shows the centre of Edwards County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Edwards County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem