SOLAR Β· ERCOT

March Road Solar

March Road Solar is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Tom Green County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19INR0147
Grid region
ERCOT (Texas)
Developer
Eon
Connection point (POI)
tap 345kV 76009 TwinB - 6444 Red Creek
Location
Tom Green County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
12 November 2017
Proposed online date
December 2021
Withdrawn
March 2020

Location

Marker shows the centre of Tom Green County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Tom Green County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem