Queue requests in study in Texas — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,486351.5 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,486 requests · page 6 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Slager Lake Wind
Onshore wind · NextEra Energy Resources Interconnection Holdings, LLC
310 MWIn study Reagan, TXERCOT Sep 2025target 2029
Sweetheart BESS
Solar + storage · Sweetheart Energy, LLC
310 MWIn study Young, TXERCOT Aug 2025target 2029
Sunrose Renewable Energy Solar SLF
Solar + storage · Sunrose Renewable Energy LLC
310 MWIn study Austin, TXERCOT Apr 2024target 2029
Red Hollow Renewable Energy Solar SLF
Solar + storage · Red Hollow Renewable Energy LLC
309 MWIn study Archer, TXERCOT Jul 2024target 2028
Buffalo Prairie Storage
Solar + storage · Buffalo Meadow Energy Center, LLC
308 MWIn study Robertson, TXERCOT Jan 2023target 2028
Clay County Yang Storage
Battery storage · DM-CCY, LLC
308 MWIn study Clay, TXERCOT Dec 2024target 2028
Mensa BESS
Battery storage · BRP Mensa BESS LLC
307 MWIn study Pecos, TXERCOT Jun 2020target 2027
18-Alpha BESS
Battery storage · SCOUT ENERGY MANAGEMENT, LLC
307 MWIn study Cooke, TXERCOT Apr 2025target 2028
Haute Stockage
Battery storage
307 MWPaused / redesign Shackelford, TXERCOT Oct 2023target 2027
Team Ranch Storage
Battery storage · BAF Storage, LLC
307 MWIn study Tarrant, TXERCOT Jun 2024target 2027
Beaujolais BESS
Battery storage
307 MWPaused / redesign Lamar, TXERCOT Dec 2023target 2026
Cattle Drive Solar
Solar · NextEra Energy Interconnection Holdings, LLC
307 MWIn study Crane, TXERCOT Jun 2024target 2029
Axtell BESS
Battery storage · Axtell BESS LLC
307 MWIn study Mclennan, TXERCOT Oct 2024target 2029
Cuchillas BESS
Solar + storage · Gransolar Texas Two
307 MWIn study Webb, TXERCOT Sep 2023target 2028
Copperleaf Energy Storage
Battery storage · Copperleaf Energy Storage, LLC
307 MWIn study Wichita, TXERCOT Nov 2024target 2029
Gilleys Energy Storage
Battery storage · Gilleys Energy Storage, LLC
306 MWIn study Wise, TXERCOT Jun 2024target 2028
Wooderson Energy Storage
Battery storage · Wooderson Energy Storage, LLC
306 MWIn study Jack, TXERCOT May 2024target 2028
Southfork Energy Storage
Battery storage · Southfork Energy Storage, LLC
306 MWIn study Kimble, TXERCOT Jul 2024target 2028
Wolf Hollow III
Gas · Wolf Hollow II Power LLC
306 MWIn study Hood, TXERCOT Jun 2023target 2027
Spur Energy Storage
Battery storage · Spur Energy Storage, LLC
306 MWIn study Wise, TXERCOT Feb 2025target 2028
Straight Spur Storage
Solar + storage · ENGIE IR Holdings LLC
306 MWIn study Andrews, TXERCOT Nov 2024target 2029
Aurora Energy Storage
Battery storage · Aurora Energy Storage, LLC
306 MWIn study Lampasas, TXERCOT Feb 2025target 2028
Damia Solar
Solar + storage · Damia Solar, LLC
306 MWIn study Eastland, TXERCOT Apr 2025target 2028
Estrella Dorada Wind
Onshore wind · Estrella Dorada Wind Farm, LLC
306 MWIn study Duval, TXERCOT Jul 2025target 2029
Velveteen Solar II
Solar · Velveteen Solar II, LLC
306 MWIn study Baylor, TXERCOT Dec 2025target 2029
Glory Bee Solar
Solar + storage · Riley Solar LLC
305 MWIn study Erath, TXERCOT Jun 2022target 2026
Lake Henry Wind
Onshore wind
305 MWPaused / redesign Kent, TXERCOT Sep 2022target 2027
Academy Wind
Onshore wind
305 MWPaused / redesign Dickens, TXERCOT Sep 2022target 2028
Glass Mountain Solar 2
Solar · Glass Mountain Solar, LLC
304 MWIn study Pecos, TXERCOT Sep 2025target 2030
WOE Gyp King Wind
Onshore wind · KSK Wind Farm 1, LLC
304 MWPaused / redesign King, TXERCOT Apr 2023target 2029
Glass Mountain Solar 1
Solar · Glass Mountain Solar, LLC
304 MWIn study Pecos, TXERCOT Sep 2025target 2028
Glass Mountain Solar Solstice
Solar · Glass Mountain Solar, LLC
304 MWIn study Pecos, TXERCOT Sep 2025target 2028
Furay Battery Energy Storage System
Battery storage · Blue Topaz 1, LLC
304 MWIn study Harris, TXERCOT Sep 2022target 2027
Juanita Creek BESS
Battery storage · Juanita Creek Energy Center, LLC
304 MWIn study Matagorda, TXERCOT Jun 2025target 2031
BRP Aras BESS
Battery storage · BRP Aras BESS LLC
304 MWIn study Upton, TXERCOT May 2021target 2028
Wander Waters BESS
Battery storage · Wander Waters BESS LLC
304 MWIn study Wilbarger, TXERCOT Mar 2024target 2027
Goat Mountain Wind-Repower
Wind + storage · Goat Wind LLC
303 MWIn study Sterling, TXERCOT Jan 2025target 2027
Prairie Power Wind
Onshore wind · Prairie Power Wind, LLC
303 MWIn study Mitchell, TXERCOT Jun 2025target 2029
Old Aqueduct Batt
Solar + storage · Old Aqueduct LLC
303 MWIn study Hale, TXERCOT May 2020target 2028
Live Oak Wind II
Onshore wind · ENGIE IR Holdings LLC
303 MWIn study Schleicher, TXERCOT Mar 2025target 2028
Brantley Branch Batt
Battery storage · Brantley Branch LLC
302 MWIn study Rusk, TXERCOT May 2020target 2029
Spurland Solar I
Solar · Spurland Solar I
302 MWIn study Dickens, TXERCOT Nov 2025target 2028
Outrider BESS
Battery storage · Sanders Hollow Energy Center, LLC
302 MWIn study Dickens, TXERCOT Jun 2025target 2028
Dry Creek Solar II
Solar · Oak Hill Solar II LLC
302 MWIn study Rusk, TXERCOT Jun 2025target 2028
Silver Dollar Solar
Solar + storage · Silver Dollar Solar Project, LLC
302 MWIn study Freestone, TXERCOT Jun 2024target 2028
Badger Solar
Solar + storage · 174 Power Global Properties, LLC
302 MWIn study Upton, TXERCOT Feb 2025target 2029
Dairyland Storage
Battery storage · ENGIE IR Holdings LLC
302 MWIn study Hopkins, TXERCOT Apr 2025target 2029
HyFuels Calhoun Solar
Solar · HyFuels Green Lake Solar LLC
302 MWIn study Victoria, TXERCOT Oct 2022target 2027
BRP Passu BESS
Battery storage · BRP Passu BESS LLC
302 MWIn study Wilbarger, TXERCOT Dec 2020target 2028
Triangle Ranch Alpha
Onshore wind · Triangle Ranch Wind
302 MWIn study Cottle, TXERCOT Oct 2022target 2029
Page 6 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)