United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 58

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 58 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Raceway Solar
Solar
10.0 MWAgreement signed Kent, DEPJM Apr 2017target 2025
Solar project AI1-126, Cumberland County
Solar
10.0 MWIn study Cumberland, VAPJM Sep 2022target 2024
Solar project J3208, Dubois County
Solar
10.0 MWIn study Dubois, INMISO Sep 2022target 2023
Wildhorse POD Solar
Solar · Highpeak Solar, LLC
10.0 MWPaused / redesign Howard, TXERCOT Oct 2023target 2026
Solar project T2-058, Box Elder County
Solar
10.0 MWIn study Box Elder, UTWest Sep 2025
Solar project IA-PNM-2017-01, Cibola County
Solar · NextEra Energy
10.0 MWAgreement signed Cibola, NMWest Jan 2017target 2021
Solar project AH2-137, Amherst County
Solar
10.0 MWIn study Amherst, VAPJM Feb 2022target 2026
Solar project AG2-166, Cumberland County
Solar · Costen Solar, Inc
10.0 MWIn study Cumberland, PAPJM Jan 2025target 2023
Solar project G1004, Franklin County
Solar
10.0 MWIn study Franklin, WAWest Nov 2023target 2025
Solar project AH1-348, Wise County
Solar · Highlands CF Solar, LLC
10.0 MWIn study Wise, VAPJM Mar 2025target 2023
SunEast Hooversville Solar
Solar
10.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
Solar project AG2-057, Morrow County
Solar · Crossroads Solar I, LLC
10.0 MWIn study Morrow, OHPJM Apr 2025target 2022
Solar project AH2-320, Cambria County
Solar
10.0 MWIn study Cambria, PAPJM Mar 2022target 2024
Solar project 968547, Marlboro County
Solar
10.0 MWIn study Marlboro, SCSoutheast Jan 2025
Solar project G0957, Benton County
Solar
10.0 MWIn study Benton, WAWest Oct 2023target 2027
Solar project 24-10021, Larimer County
Solar
10.0 MWIn study Larimer, COWest Oct 2024target 2026
NJ Land Phase II
Solar
10.0 MWPaused / redesign Burlington, NJPJM Mar 2020target 2025
Juno Solar 3
Solar · SE JUNO LLC
10.0 MWPaused / redesign Borden, TXERCOT target 2023
Solar project AH2-064, Beaver County
Solar
10.0 MWIn study Beaver, PAPJM Dec 2021target 2023
Greene County 2
Solar · Hecate Energy Greene 2 LLC
10.0 MWIn study Greene, NYNYISO Sep 2016target 2027
Solar project AH1-399, Hanover County
Solar · Ameresco Inc
9.9 MWIn study Hanover, VAPJM Feb 2025target 2023
Hollywood Solar Repower
Solar · RED TAILED HAWK SOLAR LLC
9.9 MWAgreement signed Wharton, TXERCOT target 2026
Solar project AI2-398, Preble County
Solar
9.6 MWIn study Preble, OHPJM Mar 2023target 2026
Solar project 24747, Buncombe County
Solar · Duke Energy Progress, LLC
9.5 MWAgreement signed Buncombe, NCSoutheast Dec 2016target 2026
Lillie Solar
Solar
9.4 MWAgreement signed Edgecombe, NCPJM May 2020target 2028
Solar project 956528, Dillon County
Solar
9.0 MWIn study Dillon, SCSoutheast Jun 2024
Solar project LGE-GIS-2016-001, Clark County
Solar
9.0 MWAgreement signed Clark, KYSoutheast Mar 2016target 2017
Solar project AH1-054, Ocean County
Solar · Pasadena Pemberton Solar Farm, LLC
8.3 MWIn study Ocean, NJPJM Feb 2025target 2022
Solar project SGI-PNM-2017-09, Luna County
Solar
8.3 MWAgreement signed Luna, NMWest Jun 2017target 2019
Solar project AI1-033, Somerset County
Solar
8.0 MWIn study Somerset, NJPJM Apr 2022target 2026
Solar project AH2-128, Clarion County
Solar
8.0 MWIn study Clarion, PAPJM Feb 2022target 2026
Hovey Solar 2
Solar · BARILLA SOLAR, LLC
7.5 MWIn study ERCOT Nov 2025target 2026
Solar project AH2-412, Cumberland County
Solar
7.4 MWIn study Cumberland, NJPJM Mar 2022target 2022
Solar project AI2-310, Venango County
Solar
7.3 MWIn study Venango, PAPJM Mar 2023target 2025
Solar project AH1-057, Wicomico County
Solar · Kumquat & Citron Cleantech LLC
7.2 MWIn study Wicomico, MDPJM Mar 2025target 2023
Solar
Solar
7.0 MWAgreement signed Kennebec, MEISO-NE Aug 2019target 2022
Barbertown Solar
Solar
7.0 MWPaused / redesign Hunterdon, NJPJM Mar 2020target 2026
Solar
Solar
6.8 MWAgreement signed Plymouth, MAISO-NE Jan 2018target 2019
Solar project AI2-057, Venango County
Solar
6.6 MWIn study Venango, PAPJM Feb 2023target 2024
Solar project AF2-088, Clearfield County
Solar
6.5 MWAgreement signed Clearfield, PAPJM Feb 2020target 2026
Solar project AH2-394, Lawrence County
Solar
6.3 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project AH2-389, Lawrence County
Solar
6.0 MWIn study Lawrence, PAPJM Mar 2022target 2023
Solar project J4169, Dickinson County
Solar
6.0 MWIn study Dickinson, MIMISO Oct 2025target 2025
Solar project 977121, Williamsburg County
Solar
6.0 MWIn study Williamsburg, SCSoutheast Jun 2025
National Park NJ
Solar
6.0 MWAgreement signed Gloucester, NJPJM Jun 2016target 2026
Solar project AI1-122, Sussex County
Solar
5.9 MWIn study Sussex, NJPJM Sep 2022target 2025
Solar project AI2-458, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-476, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AH2-042, Berkeley County
Solar
5.8 MWIn study Berkeley, WVPJM Nov 2021target 2024
Solar project AI2-467, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Page 58 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)