Solar project AH2-389, Lawrence County

Solar project AH2-389, Lawrence County is a 6.0 MW solar request in interconnection study in the PJM interconnection queue, in Lawrence County, Pennsylvania, connecting to ATSI.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-389
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Devlin 69 kV
Location
Lawrence County, Pennsylvania
Technology
Solar: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 March 2022
Proposed online date
December 2023

Location

Marker shows the centre of Lawrence County; the queue data does not give exact sites.