United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMSolar project AH2-389, Lawrence County
Solar project AH2-389, Lawrence County is a 6.0 MW solar request in interconnection study in the PJM interconnection queue, in Lawrence County, Pennsylvania, connecting to ATSI.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-389
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Devlin 69 kV
- Location
- Lawrence County, Pennsylvania
- Technology
- Solar: 6.0 MW
- Total requested
- 6.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- December 2023
Location
Marker shows the centre of Lawrence County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Lawrence County
- Green Meadows SolarSolar · 40.0 MW · agreement signed
- Solar project AG2-236, Lawrence CountySolar · 20.0 MW · in study
- Solar project AH2-394, Lawrence CountySolar · 6.3 MW · in study
- Hickory Run Energy StationGas · 1,000 MW · built
- New Castle Generating StationGas · 4.0 MW · built
- New Castle Generating StationGas · 1.0 MW · built
- Gas project Y1-015, Lawrence CountyGas · 1,000 MW · withdrawn
- Gas project Y1-070, Lawrence CountyGas · 825 MW · withdrawn
- Firefly SolarSolar · 202 MW · withdrawn
- Firefly SolarSolar · 200 MW · withdrawn
- Solar + storage project AG1-489, Lawrence CountySolar + storage · 175 MW · withdrawn
- Solar project AF2-253, Lawrence CountySolar · 70.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem