United States › Grid › Interconnection queues › New Jersey
SOLAR · PJMSolar project AH2-412, Cumberland County
Solar project AH2-412, Cumberland County is a 7.4 MW solar request in interconnection study in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2022 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-412
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEC
- Connection point (POI)
- TBD 69kV
- Location
- Cumberland County, New Jersey
- Technology
- Solar: 7.4 MW
- Total requested
- 7.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- December 2022
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Cumberland County
- South OrchardBattery storage · 50.0 MW · agreement signed
- South OrchardBattery storage · 30.0 MW · agreement signed
- Solar project AG2-297, Cumberland CountySolar · 19.0 MW · in study
- Cumberland 2Gas · 225 MW · built
- Clayville Unit #1Gas · 63.0 MW · built
- Howard M. Down Power Plant Unit 11Gas · 63.0 MW · built
- Carll's Corner Units 1 & 2Other · 18.0 MW · built
- Vineland Unit #9Other · 17.0 MW · built
- Sherman Avenue Unit 1Gas · 12.4 MW · built
- NJ Oak SolarSolar · 10.0 MW · built
- Cumberland Unit 1Gas · 9.4 MW · built
- Cedar Branch Solar FarmSolar · 9.2 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem