United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Cumberland 2

Cumberland 2 is a 225 MW gas request built and operating in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Sep 2005 (completed)
  2. ConsentedDec 2010 (completed)
  3. Construction (completed)
  4. OperatingDec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
P06
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Cumberland 230 kV
Location
Cumberland County, New Jersey
Technology
Gas: 225 MW
Total requested
225 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
9 September 2005
Agreement signed
14 December 2010
Proposed online date
June 2016
Came online
December 2008

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem