United States › Grid › Interconnection queues › New Jersey
GAS · PJMCumberland Unit 1
Cumberland Unit 1 is a 9.4 MW gas request built and operating in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.
Request details
- Queue ID
- T54
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEC
- Connection point (POI)
- Cumberland 138kV
- Location
- Cumberland County, New Jersey
- Technology
- Gas: 9.4 MW
- Total requested
- 9.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 21 September 2007
- Proposed online date
- August 2010
- Came online
- August 2010
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Cumberland County
- South OrchardBattery storage · 50.0 MW · agreement signed
- South OrchardBattery storage · 30.0 MW · agreement signed
- Solar project AG2-297, Cumberland CountySolar · 19.0 MW · in study
- Solar project AH2-412, Cumberland CountySolar · 7.4 MW · in study
- Cumberland 2Gas · 225 MW · built
- Clayville Unit #1Gas · 63.0 MW · built
- Howard M. Down Power Plant Unit 11Gas · 63.0 MW · built
- Carll's Corner Units 1 & 2Other · 18.0 MW · built
- Vineland Unit #9Other · 17.0 MW · built
- Sherman Avenue Unit 1Gas · 12.4 MW · built
- NJ Oak SolarSolar · 10.0 MW · built
- Cedar Branch Solar FarmSolar · 9.2 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem