NJ Oak Solar

NJ Oak Solar is a 10.0 MW solar request built and operating in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.

Queue statusOperating
  1. PlanningQueued Dec 2009 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V4-054
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Fairfield Township 12kV
Location
Cumberland County, New Jersey
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
31 December 2009
Proposed online date
December 2011
Came online
December 2011

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem