Solar project AG2-297, Cumberland County

Solar project AG2-297, Cumberland County is a 19.0 MW solar request in interconnection study in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-297
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Developer
Calpine Mid-Atlantic Development, LLC
Connection point (POI)
Cumberland 230 kV
Location
Cumberland County, New Jersey
Technology
Solar: 19.0 MW
Total requested
19.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
28 February 2025
Proposed online date
June 2023

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem