Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 52 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Ponta Power Station
Gas · WattBridge Energy, LLC
459 MWWithdrawn / abandoned Cherokee, TXERCOT Feb 2021target 2024
Leopard Storage
Battery storage
459 MWWithdrawn / abandoned Merced, CACAISO Apr 2023target 2031
Onshore wind project MPC04300, Steele County
Onshore wind
457 MWWithdrawn / abandoned Steele, NDMISO Jul 2021target 2024
Bull Run
Solar + storage
457 MWWithdrawn / abandoned Butte, CACAISO Apr 2021target 2030
Onshore wind project C1-32, Millard County
Onshore wind
456 MWWithdrawn / abandoned Millard, UTWest May 2021target 2024
NRG THW GT 138
Gas · NRG THW GT LLC
456 MWWithdrawn / abandoned ERCOT Nov 2022target 2026
Onshore wind project C2-78, Millard County
Onshore wind
456 MWWithdrawn / abandoned Millard, UTWest May 2022target 2025
Longmeadow Hybrid Solar
Solar + storage
456 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Gas project Q86, Hudson County
Gas
455 MWWithdrawn / abandoned Hudson, NJPJM Jul 2006target 2010
Gas project Z2-041, Mchenry County
Gas
455 MWWithdrawn / abandoned Mchenry, ILPJM Feb 2014target 2018
NRG Greens Bayou 9 345
Gas · NRG Texas Power LLC
455 MWWithdrawn / abandoned ERCOT Sep 2022target 2026
Gas project AH1-753, Marshall County
Gas · Calpine Mid-Atlantic Development, LLC
455 MWWithdrawn / abandoned Marshall, WVPJM target 2019
Solar + storage project 1232, Iron County
Solar + storage
455 MWWithdrawn / abandoned Iron, UTWest May 2020target 2023
Cold Creek Solar
Solar · Cold Creek Solar LLC
455 MWWithdrawn / abandoned Schleicher, TXERCOT Apr 2022target 2026
Solar + storage project G0824, Garfield County
Solar + storage
455 MWWithdrawn / abandoned Garfield, WAWest Nov 2022target 2024
Solar project GEN-2024-307, Houston County
Solar
455 MWWithdrawn / abandoned Houston, TXSPP Mar 2025target 2028
Torbino Energy Storage
Solar
455 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Staked Plains Wind 2
Onshore wind · Lincoln Clean
454 MWWithdrawn / abandoned ERCOT Mar 2016target 2019
Cape Wind Turbine Generators
Onshore wind
454 MWWithdrawn / abandoned MAISO-NE Jun 2001target 2018
Towantic Energy
Gas
452 MWWithdrawn / abandoned New Haven, CTISO-NE Apr 2007target 2014
B.L. England Station
Gas
452 MWWithdrawn / abandoned Cape May, NJPJM Feb 2012target 2021
Monarch Creek Wind (B)
Onshore wind · EDF Renewables Development, Inc.
452 MWWithdrawn / abandoned Haskell, TXERCOT Apr 2019target 2023
Garrison Energy Center
Gas
451 MWWithdrawn / abandoned New Castle, DEPJM Feb 2015target 2024
Gas project GEN-2024-053, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2032
Gas project GEN-2024-028, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2030
Sun Streams 4
Solar + storage
450 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2020target 2024
Wind
Onshore wind
450 MWWithdrawn / abandoned RIISO-NE May 2008target 2013
Solar + storage project Company PN, Lander County
Solar + storage
450 MWWithdrawn / abandoned Lander, NVWest Mar 2023target 2026
Solar project J3998, Cerro Gordo County
Solar
450 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2025target 2030
Ranchero Solar
Solar + storage
450 MWWithdrawn / abandoned Colusa, CACAISO Apr 2019target 2023
Solar + storage project 20220118001, Richland County
Solar + storage
450 MWWithdrawn / abandoned Richland, SCSoutheast target 2024
Solar + storage project G0729, Douglas County
Solar + storage
450 MWWithdrawn / abandoned Douglas, WAWest Feb 2022target 2025
Solar project Q482, Maricopa County
Solar
450 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2026
Onshore wind project GI-2008-10, Morgan County
Onshore wind
450 MWWithdrawn / abandoned Morgan, COWest Jun 2008target 2011
Offshore wind project R37, Sussex County
Offshore wind
450 MWWithdrawn / abandoned Sussex, DEPJM Nov 2006target 2014
Onshore wind project C3-185, Carbon County
Onshore wind
450 MWWithdrawn / abandoned Carbon, WYWest May 2023target 2028
Bonanza Solar 2
Solar + storage
450 MWWithdrawn / abandoned Clark, NVCAISO Apr 2020target 2024
Solar + storage project G0940, Gilliam County
Solar + storage
450 MWWithdrawn / abandoned Gilliam, ORWest Sep 2023target 2027
LA450S
Solar
450 MWWithdrawn / abandoned Luna, NMWest Sep 2016target 2019
Onshore wind project J4135, Grant County
Onshore wind
450 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Gas project A58, Prince George's County
Gas
450 MWWithdrawn / abandoned Prince George's, MDPJM Mar 1999
FRV Eafb Solar
Solar
450 MWWithdrawn / abandoned Kern, CACAISO Feb 2010target 2013
Solar + storage project PIS045, Morrow County
Solar + storage
450 MWWithdrawn / abandoned Morrow, ORWest Dec 2023target 2027
Other project AI1-202, Grant County
Other
450 MWWithdrawn / abandoned Grant, WVPJM Sep 2022target 2026
Battery storage project J2624, Stevens County
Battery storage
450 MWWithdrawn / abandoned Stevens, MNMISO Sep 2022target 2026
Solar project Q193, Maricopa County
Solar
450 MWWithdrawn / abandoned Maricopa, AZWest Mar 2011target 2015
Solar project C4-086, Emery County
Solar
450 MWWithdrawn / abandoned Emery, UTWest May 2024target 2029
Solar project J3408, Sabine Parish County
Solar
450 MWWithdrawn / abandoned Sabine Parish, LAMISO Apr 2024target 2028
Gas project 106, Hernando County
Gas · Masked
450 MWWithdrawn / abandoned Hernando, FLSoutheast Aug 2010target 2014
Gas project Q4, Pinal County
Gas
450 MWWithdrawn / abandoned Pinal, AZWest Mar 2005target 2001
Page 52 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)