πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project C3-185, Carbon County

Onshore wind project C3-185, Carbon County is a 450 MW onshore wind request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-185
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Aeolus substation
Location
Carbon County, Wyoming
Technology
Wind: 450 MW
Total requested
450 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2023
Proposed online date
November 2028

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem