SOLAR Β· SPPSolar project GEN-2024-307, Houston County
Solar project GEN-2024-307, Houston County is a 455 MW solar request withdrawn in the SPP interconnection queue, in Houston County, Texas, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-307
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Crockett 345 kV Substation
- Location
- Houston County, Texas
- Technology
- Solar: 455 MW
- Total requested
- 455 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 March 2025
- Proposed online date
- October 2028
- Withdrawn
- December 2025
Location
Marker shows the centre of Houston County; the queue data does not give exact sites.
Other requests in Houston County
- Camino Ranch Storage SLFSolar + storage Β· 298 MW Β· in study
- Camino Ranch Solar SLFSolar + storage Β· 296 MW Β· in study
- Solar project GEN-2024-232, Houston CountySolar Β· 250 MW Β· in study
- Camino Ranch Storage 2 SLFSolar + storage Β· 239 MW Β· in study
- Camino Ranch Solar 2 SLFSolar + storage Β· 237 MW Β· in study
- Saint Charles Energy StorageBattery storage Β· 203 MW Β· in study
- Leon BESSSolar + storage Β· 154 MW Β· in study
- Dionysus SolarSolar + storage Β· 153 MW Β· in study
- Houston County BESSBattery storage Β· 125 MW Β· in study
- Dionysus StorageSolar + storage Β· 77.3 MW Β· in study
- Solar project J3441, Houston CountySolar Β· 500 MW Β· withdrawn
- Battery storage project J4104, Houston CountyBattery storage Β· 250 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem