BATTERY STORAGE · ERCOT

Saint Charles Energy Storage

Saint Charles Energy Storage is a 203 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Houston County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0363
Grid region
ERCOT (Texas)
Developer
RSN STORAGE 001, LLC
Connection point (POI)
TAP 138kV 3345 FLATBRA_8 - 3351 JIM_ENG_8
Location
Houston County, Texas
Technology
Battery: 203 MW
Total requested
203 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 February 2024
Proposed online date
June 2027

Location

Marker shows the centre of Houston County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Houston County